The CHBA Board Officers are putting together plans to help this project go as smoothly as we can. The contractor has asked us to provide them one point of contact for any and all questions about the project. If you have a question please call Michelle 440-946-4826 or Danielle 440-221-1787 or email the association (chagrinhba@gmail.com) your question and we will forward it to the contractor to get an answer for you.
Frequently Asked Questions (FAQ) page
Click here to read the Contractor's Letter that went out to everyone in the neighborhood the week of October 26th.
Projected Completion is end of September 2021
Area A estimated duration is 23 days - 30 days.
Area B estimated duration is 18 days - 28 days
Area C estimated duration is 22 days - 24 days
Area D estimated duration is 17 days - 24 days
Area E estimated duration is 11 days - 24 days
Area F estimated duration is 9 days - 19 days
Area G estimated duration is 6 days - 24 days
Area H estimated duration is 22 days
Closeout duration is 49 days
* All durations are dependent on weather and unforeseen complications. This schedule can change as the project progresses either speeding up or slowing down. Please only refer to this as a guide and not as a strict timeframe.
The sub-contractor will be starting on asphalt driveway aprons first thing in the morning 05/19. This should take about 2-4 hours to complete. They will continue on Friday May 20th with any streets they don’t get to on Thursday.